Items |
Unit |
HZS120/2HZS120 |
|
Theoretical productivity |
m3/h |
120/240 |
|
Dump height |
m |
4 |
|
Model of main mixing machine |
|
MAO3000/2000 |
|
Mixing power |
kW |
2X37 |
|
Nominal volume of main mixing machine |
L |
2000 |
|
Production cycle |
s |
60 |
|
Aggregate diameter |
mm |
≤80 |
|
Aggregate bin volume |
m3 |
4X25 |
|
Powder bin (optional)volume |
t |
4×200 |
|
Batching plant capacity |
L/bin |
3200 |
|
Inclined belt conveyor capacity |
t/h |
900 |
|
Concrete spiral conveyor capacity |
t/h |
90 |
|
Coal ash spiral conveyor capacity |
t/h |
60 |
|
Standard installed capacity |
kW |
210/420 |
|
Weighing range & accuracy of sand/stone |
kg |
(0~3600)±2% |
|
Weighing range & accuracy of cement |
kg |
(0~1000)±1% |
|
Weighing range & accuracy of coal ash |
kg |
(0~500)±1% |
|
Weighing range & accuracy of water |
kg |
(0~500)±1% |
|
Weighing range & accuracy of additives |
kg |
(0~50)±1% |